Public contracts of Barbezieux-Saint-Hilaire · 2026 · Construction and buildings

Accord-cadre 2026-2030 travaux sur réseaux d’eau potable et d’assainissement des eaux usées canalisation et équipements divers

€2.8M
framework agreement: a maximum envelope for orders over 5 years, not spending — what was paid on it is not published
Signed on 10 September 2026 · running until about September 2031 · 5 yrs
Ongoing10 Sept 2031

That is at most ~€560k a year on average: a maximum too.

Company selected

Entr Régionale Canalisations Travaux PubConstruction de réseaux pour fluides · registered office Boulazac Isle Manoire (24330) · headcount 100 to 199 employees · SIREN 551980469

The competition

2 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

It belongs to the policy Environment and cleanliness.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.