Public contracts of Basse-Terre · 2022 · Transport and vehicles

Contrôle d’accès du parking campenon rue ALI TUR

€91k
contract ceiling — what was paid on it is not published
Signed on 24 October 2022 · ended around January 2023 · 3 months

Who won it

Hitachi Rail RCS France SASConception d'ensemble et assemblage sur site industriel d'équipements de contrôle des processus industriels · registered office Le Plessis-Pate (91220) · headcount 250 to 499 employees · SIREN 823356936
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no