Public contracts of Bastia · 2019 · Construction and buildings

Restructuration de l’école Gaudin

€420k
maximum contract amount over 10 months — what was paid on it is not published
Signed on 12 September 2019 · ended around July 2020 · 10 months

Company selected

VO2Travaux d'installation d'équipements thermiques et de climatisation · registered office Biguglia (20620) · headcount 20 to 49 employees · SIREN 422786137

Number 11 by amount of the 67 contracts Bastia published for 2019. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.