Public contracts of Béziers · 2019 · Construction and buildings

070 GS PElisson couvertures-Groupe scolaire Pelisson

Réfection des couvertures

€126k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 23 May 2019 · ended around July 2019 · 2 months

Company selected

Établissement BouzatImprégnation du bois · registered office Beziers (34500) · headcount 20 to 49 employees · SIREN 421495763

Number 115 by amount of the 390 contracts Béziers published for 2019. It belongs to the policy Schools.

Other contracts of Établissement Bouzat in Béziers

École barbeyrac : réfection des couvertures2026 · maximum over 3 months141€kÉcole babeyrac2026 · maximum over 6 months141€kHalle des sports du four a chaux2024 · maximum over 4 months263€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.