Skip to main content

Public contracts of Béziers · 2020 · Construction and buildings

Reconstruction Les Tamaris-Clos : couverture, façade

€1.9M
maximum contract amount over 14 months — what was paid on it is not published
Signed on 10 July 2020 · ended around September 2021 · 14 months

That is at most ~€1.6M a year on average: a maximum too.

Company selected

Construction Générale du Ceressou (CGC)Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Adissan (34230) · headcount 10 to 19 employees · SIREN 404244808

Number 7 by amount of the 199 contracts Béziers published for 2020.

Other contracts of Construction Générale du Ceressou (CGC) in Béziers

Rouge gorge2024 · maximum over 5 months87€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.