Public contracts of Bihorel · 2024

Travaux de rénovation énergétique et d’accessibilité de l’école élémentaire haingere et de l’accueil de loisirs COTY lot 3

The largest contract Bihorel awarded in 2024, out of 30.

Contract · Construction and Bâtiment · Travaux · carried out in 76420 · environmental clauses

296k €
contract ceiling — what was paid on it is not published
Signed on 4 June 2024 · ended around January 2025 · 0.6 yrs
Ended3 Jan 2025

Who won it

Entreprise RavetSIREN 432820942

The competition

4 bids received

Adapted procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendmentsnone
Subcontracting declaredyes
Environmental considerationsCritère environnemental, Clause environnementale

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method