Skip to main content

Public contracts of Biscarrosse · 2026 · Construction and buildings

De répondre aux besoins de la commune de Biscarrosse en matière de travaux d’entretien et travaux neufs du patrimoine bâti communal

Occultation · Stores…

€40k
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 31 March 2026 · running until about March 2030 · 4 yrs
Ongoing31 Mar 2030

That is at most ~€10k a year on average: a maximum too.

Company selected

France Menuisiers (Ridoret Énergie)Travaux de menuiserie bois et PVC · registered office La Rochelle (17000) · headcount 100 to 199 employees · SIREN 433464997

The competition

2 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 76 by amount of the 110 contracts Biscarrosse published for 2026.

Other contracts of France Menuisiers (Ridoret Énergie) in Biscarrosse

De répondre aux besoins de la commune de Biscarrosse en matière de…2026 · maximum over 4 years144€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.