Travaux de réhabilitation du plateau sportif du gymnase du Ried à Bischheim (lot unique)

Number 11 by amount of the 48 contracts Bischheim awarded in 2025.

Contract · Construction and Bâtiment · Travaux · carried out in 67

447k €
contract ceiling — what was paid on it is not published
Signed on 5 November 2025 · ended around May 2026 · 0.5 yrs
Ended7 May 2026

Who won it

E.P.S.L.SIREN 833970684

The competition

3 bids received

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendmentsnone
Subcontracting declaredyes

Other contracts of E.P.S.L. in Bischheim

Travaux plateau sportif2026449k€Réalisation d’un terrain de football synthétique2024498k€Terrain foot synthétique stade fc soleil2024488k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method