Public contracts of Bize · 2023 · Construction and buildings

Création

€1.3M
maximum contract amount over 13 months — what was paid on it is not published
Signed on 20 June 2023 · ended around July 2024 · 13 months

That is at most ~€1.2M a year on average: a maximum too.

Company selected

LorenziTravaux de peinture et vitrerie · registered office Ibos (65420) · headcount 100 to 199 employees · SIREN 317807444

A contract awarded to 11 holders; above, the main holder. With it: Bajon et Andres, Nouvelle Assainissement Adduction D Eau, Les Menuisiers Bagnerais, GMT, Menuisiers Agenceurs de Bigorre, Oliveira Rogel, SARL Menuiserie Perez, Entreprise Gallart Bati-Comminges, Montes (Plomberie Chauffage Électricité Climatisation Fourniture Pose de Pompe), CTB. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 8 contracts Bize published for 2023.

Other contracts of Lorenzi in Bize

Création d’une résidence senior Le Cazala2023 · maximum over 13 months41€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Ferme

Published amendments : none