Public contracts of Bouc-Bel-Air · 2025 · Construction and buildings

Travaux de réfection de la salle Antonin Gabelier pour la ville de Bouc-Bel-Air

€32k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 30 July 2025 · ended around December 2025 · 5 months

Company selected

BmbtpConstruction d'autres bâtiments · registered office Saint-Maximin-La-Sainte-Baume (83470) · headcount 1 or 2 employees · SIREN 811303510

The competition

9 bids received

Median for this procedure in 2025: 3 bids, across 48929 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 7 by amount of the 8 contracts Bouc-Bel-Air published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Critère environnemental, Clause environnementale