Skip to main content

Public contracts of Boulange · 2024 · Construction and buildings

Reconstruction du complexe sportif : structure bois

€880k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 4 January 2024 · ended around January 2026 · 2 yrs

That is at most ~€440k a year on average: a maximum too.

Company selected

Le Bras FreresTravaux de charpente · registered office Jarny (54800) · headcount 100 to 199 employees · SIREN 320182447

The competition

5 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 14 contracts Boulange published for 2024.

Other contracts of Le Bras Freres in Boulange

Reconstruction du complexe sportif : bardage et couverture2024 · maximum over 2 years616€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.