Public contracts of Bourges · 2024 · Construction and buildings

Création d’un local SNG et d’un local poubelle dans l’ancien hôtel de ville

Démolition gros oeuvre

€41k
maximum contract amount over 9 months — what was paid on it is not published
Signed on 30 April 2024 · ended around January 2025 · 9 months

Company selected

Art ConstructionTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Saint-Doulchard (18230) · headcount 6 to 9 employees · SIREN 399629401

Number 117 by amount of the 119 contracts Bourges published for 2024. It belongs to the policy Administration and shared services.

Other contracts of Art Construction in Bourges

Fissuration école elemnetaire grand meaulnes travaux de sous oeuvre2025 · maximum over 2 months89€kRéaménagement rdc médiathèque2022 · maximum over 8 months58€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.