Skip to main content

Public contracts of Brazey-en-Plaine · 2024 · Professional services

Maîtrise d’œuvre pour la rénovation énergétique et la mise aux normes de l’école maternelle

€151k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 7 May 2024 · ended around May 2026 · 2 yrs

That is at most ~€76k a year on average: a maximum too.

Company selected

Bureau d'Études Techniques Construction (Ekoliance)Ingénierie, études techniques · registered office Marsannay-La-Cote (21160) · headcount 10 to 19 employees · SIREN 303477657

A contract awarded to a consortium of 3 holders; above, the main holder. With it: Bureau d'Architecture et d'Urbanisme, Bureau d'Études Techniques Daventure (Bet Daventure). The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 3 by amount of the 3 contracts Brazey-en-Plaine published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.