Public contracts of Brie-Comte-Robert · 2023 · Construction and buildings

Réhabilitation et extension du complexe sportif Arthur Chaussy

Travaux pour remettre en état et agrandir le complexe sportif Arthur Chaussy.

€82k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 31 May 2023 · running until about May 2027 · 4 yrs
Ongoing1 May 2027

That is at most ~€21k a year on average: a maximum too.

Company selected

Établissements HannyTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Vaux-Le-Penil (77000) · headcount 100 to 199 employees · SIREN 786350157

The competition

1 bid received

Median for this procedure in 2023: 3 bids, across 8316 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 16 by amount of the 21 contracts Brie-Comte-Robert published for 2023. It belongs to the policy Culture, sport and youth.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 2