Skip to main content

Public contracts of Brignais · 2021 · Construction and buildings

Réhabilitation et extension du groupe scolaire Jean Moulin : façades, isolation par l’extérieur

€257k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 29 November 2021 · ended around December 2023 · 2 yrs

That is at most ~€123k a year on average: a maximum too.

Company selected

SAS NebihuTravaux de plâtrerie · registered office Neyron (01700) · headcount 50 to 99 employees · SIREN 522604644

Number 6 by amount of the 21 contracts Brignais published for 2021. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.