Public contracts of Brissac Loire Aubance · 2026 · Construction and buildings

Réhabilitation de l’école : électricité, courants forts et faibles

€225k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 13 May 2026 · running until about August 2027 · 15 months
Ongoing13 Aug 2027

That is at most ~€180k a year on average: a maximum too.

Company selected

Spie Building SolutionsTravaux d'installation électrique dans tous locaux · registered office Saint-Ouen-Sur-Seine (93400) · headcount 2,000 to 4,999 employees · SIREN 440055861

The competition

5 bids received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 6 by amount of the 16 contracts Brissac Loire Aubance published for 2026. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.