Skip to main content

Public contracts of Bruges · 2026 · Construction and buildings

Travaux relatifs à la fermeture partielle des façades de la halle Galinier à Bruges

Charpente métallique

€111k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 3 July 2026 · running until about November 2026 · 4 months
Ongoing2 Nov 2026

Who won it

Julien LavoineTravaux de charpente · registered office Merignac (33700) · headcount 20 to 49 employees · SIREN 753553114

The competition

1 bid received

Median for this procedure in 2026: 1 bid, across 1931 comparable contracts. Contract awarded without prior advertising or competitive bidding · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 3 by amount of the 23 contracts Bruges published for 2026. It belongs to the policy Economy and trade.

Other contracts of Julien Lavoine in Bruges

Rénovation du couvert et de solarisation de la salle Majau2025 · maximum over 9 months293€k
Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.