Bussy-Saint-Georges: where the money goes
The public contracts of Bussy-Saint-Georges
Up to €44.1M: the maximum amount of the public contracts signed in 2025, over their whole term.
91 contracts in 2025 · €151.4M published from 2018 to 2026. Maximum amounts planned.
Contracts state a maximum amount for their whole term, often several years. That amount differs from what was paid.
6 contracts of 2025 (€905.4M published) are left out of the total and the lists: the same ceiling copied onto the lots of one framework agreement, the same publication twice, a framework ceiling above a quarter of the town’s yearly spending, or an out-of-scale amount.
Contracts signed by year
Click a year to see its contracts
Purchases by category, 2018–2026
Click a category to see its contracts
The 7 other categories
Main contracts of 2025
Click a contract to see its fiche
- Nettoiement des voies communales et espaces publicsJCT Environnement · 2 lotsup to €21M
- Bail du passage Carter : volumes 25, 26, 27, 31, 32 et 49Myrisup to €3.4M
- Requalification de l’hypercentre : voirie et réseaux divers, éclairage, vidéoprotectionEurovia Ile de Franceup to €2.8M
- Voirie et réseaux divers, maçonnerie, vidéoprotection, éclairage et mobilier urbainOise Environnement Travaux Publics · consortium of 2 holders, whole-contract amountup to €2.8M
- Travaux neufs et entretien de voirie et réseaux diversColas France · consortium of 3 holders, whole-contract amount · framework agreement: a maximum envelope, not spendingup to €2M
- Bail du passage Carter, volumes 29 et 30Myrisup to €1.2M
- Exploitation du réseau de production et de distribution d’énergieBussycomore Énergieup to €1.2M
- Nettoyage des groupes scolaires, centres de loisirs et bâtiments périscolairesEuro Defense Service (Groupe la Brenne) · framework agreement: a maximum envelope, not spendingup to €719k
- Nettoyage des groupes scolairesEuro Defense Service (Groupe la Brenne) · framework agreement: a maximum envelope, not spendingup to €719k
- Paysage Arrosage BrumisationGroupe Loiseleur Hauts de France Grand Paris · consortium of 2 holders, whole-contract amountup to €610k
The 79 other contracts of 2025
- Requalification des abords des tennis couverts : voirie et réseaux divers, espaces vertsMedinger et Fils Trav Publicup to €544k
- ÉtanchéitéAstenup to €535k
- Trx réhabilitation terrain synthétique du complexe herzogProgreen · consortium of 2 holders, whole-contract amountup to €512k
- Travaux de réhabilitation du terrain synthétique du complexe sportif Maurice Herzog de la…Voirie et réseaux divers terrain de sport · Progreenup to €512k
- Bibou Le Hibou Les LuciolesLPCR CDF (les Petits Chaperons Rouges Orleans Patay)up to €490k
- Location et maintenance de copieurs pour la Mairie et les groupes scolairesAvenir Solutions Numeriquesup to €354k
- Location et maintenance des copieurs pour les services municipaux…Location et maintenance de copieurs pour la Mairie et les groupes… · Avenir Solutions Numeriques · framework agreement: a maximum envelope, not spendingup to €354k
- Mobilier de bureauGoujon Bureau · framework agreement: a maximum envelope, not spendingup to €300k
- Graines de paradisLa Maison Bleue Bussyup to €274k
- Ossature métalliqueBray CMup to €188k
- Petit à PetitLa Maison Bleue Bussyup to €186k
- Requalification de l’hypercentre, Grand place et avenue du Général de Gaulle : étanchéitéAstenup to €172k
- Fourniture de mobilier et d’équipements pour le groupe scolaire n°13 Arnaud Beltrame de…Mobilier scolaire · Manutan Collectivites · framework agreement: a maximum envelope, not spendingup to €145k
- Mobilier scolaireManutan Collectivitesup to €145k
- Signalisation horizontaleIDF Marquage · framework agreement: a maximum envelope, not spendingup to €120k
- Signalisation routière verticale et horizontale pour la Ville de Bussy-Saint-GeorgesSignalisation Horizontale · IDF Marquage · framework agreement: a maximum envelope, not spendingup to €120k
- Portage des repas à domicile pour le CCAS de la Ville de Bussy-Saint-GeorgesSaveurs et Vie · framework agreement: a maximum envelope, not spendingup to €110k
- Portage des repas à domicile pour le CCAS de la Ville de Bussy-Saint-GeorgesSaveurs et Vie Conseil · framework agreement: a maximum envelope, not spendingup to €110k
- Maintenance des systèmes de sureté électronique dans les bâtiments de la Ville de…Delta Security Solutions · 2 lots · framework agreement: a maximum envelope, not spendingup to €107k
- Fournitures scolaires et petits équipementsPapeteries Pichon · framework agreement: a maximum envelope, not spendingup to €100k
- Acquisition de fournitures administratives de bureau, fournitures scolaires…Fournitures scolaires et petits… · Papeteries Pichon · framework agreement: a maximum envelope, not spendingup to €100k
- VidéoprotectionSerfim T.I.C. · framework agreement: a maximum envelope, not spendingup to €100k
- Fourniture de carburants à la pompe et d’électricité aux bornes de recharge par cartes…Greenway · framework agreement: a maximum envelope, not spendingup to €90k
- Maîtrise d’œuvre pour la réalisation de 6 vestiaires au complexe sportif Maurice Herzog à…Petr Architectesup to €81k
- Location, installation et démontage de stands, de matériels et d’accessoires…International Modulingup to €76k
- Forum de l’emploi 2026-2029International Modulingup to €76k
- Maîtrise dœuvre pour la réalisation de 6 vestiaires au complexe sportif Maurice HerzogPetr Architectes · consortium of 2 holders, whole-contract amountup to €69k
- Réalisation, conception, impression et livraison d’affiches, carte de visite, flyers…Le Reveil de la Marne · framework agreement: a maximum envelope, not spendingup to €65k
- Réalisation, conception, impression et livraison d’affiches, carte de visite, flyers…Le Reveil de la Marne · framework agreement: a maximum envelope, not spendingup to €65k
- Collecte, d’impression, de mise sous pli et d’affranchissement de courrier…Courrier Plus · framework agreement: a maximum envelope, not spendingup to €62k
- Collecte impression mise sous pli affranchissement courrierPostalia France · framework agreement: a maximum envelope, not spendingup to €60k
- Gestion d’accueil de loisirs pour les 11-14 ans durant les vacances scolairesScenoconcept · framework agreement: a maximum envelope, not spendingup to €55k
- Gestion d’accueil de loisirs pour les 11-14 ansScenoconcept · framework agreement: a maximum envelope, not spendingup to €55k
- Acquisition de matériels pédagogiques pour les enfants de 0 à 11 ans…Matériels pédagogiques pour les enfants de 3 à 11ans · As Distribution (Erget Buro) · framework agreement: a maximum envelope, not spendingup to €50k
- Matériel pédagogique pour les 3-11 ansAs Distribution (Erget Buro) · framework agreement: a maximum envelope, not spendingup to €50k
- Maintenance et d’exploitation de la solution Wifi pour la ville de Bussy-Saint-Georges…Qos Telecom · framework agreement: a maximum envelope, not spendingup to €50k
- Maintenance et exploitation d’une solution wifiQos Telecom · framework agreement: a maximum envelope, not spendingup to €50k
- Intrusion, vidéosurveillance et services exclusifsDelta Security Solutions · framework agreement: a maximum envelope, not spendingup to €50k
- Signalisation verticaleCity Signa · 2 holders, whole-contract amount · framework agreement: a maximum envelope, not spendingup to €50k
- Signalisation routière verticale et horizontale pour la Ville de Bussy-Saint-GeorgesSignalisation Verticale · City Signa · framework agreement: a maximum envelope, not spendingup to €50k
Main suppliers, 2018–2026
Click a company to see its contracts
- Ifac2 contractsup to €29M
- JCT Environnement2 contractsup to €21M
- Ipf 78 (Agence Paris Est)1 contractup to €5M
- Myris2 contractsup to €4.6M
- Lachaux Paysage2 contractsup to €4.2M
- Euro Defense Service (Groupe la Brenne)3 contractsup to €3.7M
- Eurovia Ile de France2 contractsup to €3.6M
- Manutan Collectivites3 contractsup to €3.3M
The 185 other suppliers
- Euro Vert1 contractup to €3.2M
- Soldrain Sols Sportifs2 contractsup to €2.9M
- Maintenance Industrie1 contractup to €2.8M
- Oise Environnement Travaux Publics1 contractup to €2.8M
- Phasellus Bâtiment1 contractup to €2.4M
- Engie Énergie Services (Ees IDF Habitat et Collectivites 2)1 contractup to €2.3M
- Colas France2 contractsup to €2.2M
- Saint Germain Paysage2 contractsup to €2M
- Ib Elec1 contractup to €2M
- SN Perfect Europeenne de Nettoyage2 contractsup to €1.9M
- Gfer1 contractup to €1.8M
- Idverde (Ile de France Est Maintenance)1 contractup to €1.8M
- Soin des Arbres en Milieu Urbain2 contractsup to €1.5M
- Snef9 contractsup to €1.5M
- Aluminium Fabrication Diffusion2 contractsup to €1.4M
- Sma2 contractsup to €1.4M
- 3 C.D.B. Agencement2 contractsup to €1.3M
- Pro Evolution Bat S (Peb)2 contractsup to €1.3M
- Plug And Play4 contractsup to €1.3M
- Guilbert Proprete2 contractsup to €1.2M
- Urbatec Ingenierie3 contractsup to €1.2M
- Bussycomore Énergie1 contractup to €1.2M
- Premys (Agence Brunel)2 contractsup to €1.2M
- Makesoft1 contractup to €1.2M
- Progreen2 contractsup to €1M
- La Société des Revetements et Peinture1 contractup to €900k
- Chapelec (Etancheite Asphalte Cuvelage Inj)1 contractup to €900k
- Polytan France2 contractsup to €875k
- As Distribution (Erget Buro)8 contractsup to €822k
- Avenir Solutions Numeriques4 contractsup to €788k
- Hemera Service Proprete1 contractup to €763k
- Etel1 contractup to €750k
- Satelec1 contractup to €724k
- Asten2 contractsup to €707k
- Aximum2 contractsup to €680k
- Acorus - Peintisol2 contractsup to €612k
- Établissements Reithler1 contractup to €610k
- Swile1 contractup to €610k
- Groupe Loiseleur Hauts de France Grand Paris1 contractup to €610k
- Conception Realisation de Menuiseries1 contractup to €600k
- JMC1 contractup to €600k
- Prodesign2 contractsup to €583k
Understanding these figures
What does a contract’s amount measure?
A contract’s amount is the maximum allowed over its whole term, often several years: it is not what the town spends in the year. The lots of one contract are grouped.
Where do these figures come from?
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.
Source: Public procurement — DECP (data.gouv.fr) ↗, consolidated and checked by Colin Maudry (colibre.fr ↗)