Skip to main content

Public contracts of Calais · 2019 · Construction and buildings

Pose d’un columbarium d’un module unique de forme murale au cimetiére sud de la ville de Calais

€10k
maximum contract amount over 4 months — what was paid on it is not published
Signed on 15 October 2019 · ended around February 2020 · 4 months

Company selected

VGS - Art Groupe SBT ColumbariumServices funéraires · registered office Longfosse (62240) · headcount 1 or 2 employees · SIREN 539814681

Number 140 by amount of the 170 contracts Calais published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.