Skip to main content

Public contracts of Cassel · 2025 · Construction and buildings

Réhabilitation et extension de la salle des sports : charpente bois

€155k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 6 August 2025 · ended around September 2026 · 13 months

That is at most ~€143k a year on average: a maximum too.

Company selected

Charpentier des FlandresTravaux de charpente · registered office Meteren (59270) · headcount 10 to 19 employees · SIREN 380804492

Number 5 by amount of the 10 contracts Cassel published for 2025.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.