Skip to main content

Public contracts of Cavaillon · 2022 · Construction and buildings

Rénovation énergétique de 3 écoles : chauffage et chaufferie du groupe scolaire La Colline

€164k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 12 September 2022 · ended around September 2023 · 12 months

Company selected

NeotechTravaux d'installation électrique dans tous locaux · registered office Taillades (84300) · headcount 20 to 49 employees · SIREN 814911848

Number 8 by amount of the 31 contracts Cavaillon published for 2022. It belongs to the policy Schools.

Other contracts of Neotech in Cavaillon

Travaux de mise en conformité des réseaux de distribution d’eau chaude…2025 · maximum over 3 months65€kRéhabilitation partielle de l’école castil Blaze2024 · maximum over 5 months14€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.