Public contracts of Celles-sur-Belle · 2024 · Other

Maîtrise d’œuvre : construction des ateliers municipaux

€162k
contract ceiling — what was paid on it is not published
Signed on 27 September 2024 · ended around April 2026 · 19 months

Who won it

SecobaActivité des économistes de la construction · registered office Poitiers (86000) · headcount 3 to 5 employees · SIREN 326380581

Main holder, with the largest amount. The contract has 5 holders; the others are not shown here yet.

Number 2 by amount of the 4 contracts Celles-sur-Belle published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.