Public contracts of Cernay · 2022 · Construction and buildings

Club House complexe Daniel Eck à Cernay

Carrelages

€18k
maximum contract amount over 1 month — what was paid on it is not published
Signed on 27 July 2022 · ended around August 2022 · 1 month

Company selected

MultisolsTravaux de revêtement des sols et des murs · registered office Colmar (68000) · headcount 20 to 49 employees · SIREN 383459245

Number 65 by amount of the 74 contracts Cernay published for 2022.

Other contracts of Multisols in Cernay

Extension de l’Hôtel de Ville2024 · maximum over 1 month13€kExtension de l’Hôtel de Ville2024 · maximum over 1 month11€kRestructuration du Centre technique municipal2022 · maximum over 2 months36€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.