Démolition - Gros Oeuvre

Number 35 by amount of the 38 contracts Challans awarded in 2024.

Original label (DECP) : « Démolition - Gros Oeuvre » · Contract · Construction and Bâtiment · carried out in 85047

49k €
contract ceiling — what was paid on it is not published
Signed on 16 April 2024 · ended around October 2024 · 0.5 yrs
Ended16 Oct 2024

Who won it

Maurice Leroy et FilsSIREN 301853602

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendmentsnone

Other contracts of Maurice Leroy et Fils in Challans

Réhabilitation intérieure école victor hugo lot 1202679k€Gros Œuvre - renforcement structurel2025184k€Couverture bac zinc2025133k€Couverture bac zinc2024133k€Gros Œuvre - renforcement structurel2022183k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method