Public contracts of Châlons-en-Champagne · 2020 · Construction and buildings

Déploiement de la Fibre Optique : Rue du Groupe libération Nord

€26k
maximum contract amount over 2 months — what was paid on it is not published
Signed on 14 December 2020 · ended around February 2021 · 2 months

Company selected

Gtie Cap InfrasConstruction de réseaux électriques et de télécommunications · registered office Chateau-Thierry (02400) · headcount 100 to 199 employees · SIREN 414688879

Number 34 by amount of the 39 contracts Châlons-en-Champagne published for 2020.

Other contracts of Gtie Cap Infras in Châlons-en-Champagne

Requalification du parvis de la gare et création d’un pôle d’échanges…2021 · maximum over 2 months167€kRequalification de l’îlot Saint-Dominique : voie Clémangis et rue de…2021 · maximum over 6 months26€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none