Public contracts of Chamant · 2019 · Construction and buildings

Construction de la mairie

€28k
maximum contract amount over 7 months — what was paid on it is not published
Signed on 22 January 2019 · ended around August 2019 · 7 months

Company selected

SpridTravaux de peinture et vitrerie · registered office Allonne (60000) · headcount 50 to 99 employees · SIREN 784155947

Number 8 by amount of the 12 contracts Chamant published for 2019.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : 1

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.