Skip to main content

Public contracts of Chambéry · 2024 · Construction and buildings

Travaux rénov energet Travaux connexes paul bert

Démolition gros oeuvre faïence

€127k
maximum contract amount over 13 months — what was paid on it is not published
Signed on 11 July 2024 · ended around August 2025 · 13 months

That is at most ~€117k a year on average: a maximum too.

Company selected

DMTravaux de démolition · registered office Seyssins (38180) · headcount 20 to 49 employees · SIREN 538013814

Number 57 by amount of the 106 contracts Chambéry published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.