Construction d’une nouvelle station d’épuration

La commune fait construire une nouvelle station d'épuration, l'installation qui nettoie les eaux usées avant de les rejeter.

€783k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 24 March 2023 · ended around September 2023 · 6 months

Company selected

PveFabrication d'éléments en béton pour la construction · registered office Mortagne-Sur-Sevre (85290) · headcount 20 to 49 employees · SIREN 414952606

A contract awarded to 3 holders; above, the main holder. With it: BHD Environnement, E.R.S.E (Etude Realisation de Station d'Epuration). The amount is the whole contract’s: the DECP does not publish each holder’s share.

The largest of the 3 contracts Champigny-sur-Veude published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.