Skip to main content

Public contracts of Charleville-Mézières · 2025 · Construction and buildings

Façades

€82k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 6 January 2025 · ended around April 2026 · 15 months

That is at most ~€66k a year on average: a maximum too.

Company selected

Ardenne Peinture EvolutionTravaux d'isolation · registered office Belval (08090) · headcount 50 to 99 employees · SIREN 301296463

The competition

2 bids received

Median for this procedure in 2025: 3 bids, across 49612 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 100 by amount of the 116 contracts Charleville-Mézières published for 2025.

Other contracts of Ardenne Peinture Evolution in Charleville-Mézières

Isolation thermique par l’extérieur groupe scolaire Louis HANOT…2025 · maximum over 3 months221€kIsolation thermique par l’extérieur groupe scolaire Louis HANOT…2025 · maximum over 3 months220€kRéhabilitation du Stade Salengro ; Façades2025 · maximum over 11 months82€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 5

Social considerations : Clause sociale

Environmental considerations : Clause environnementale, Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.