L’opération de travaux a pour objet la transformation de deux bâtiments en ERP situé 11, 20 chemin de l’observatoire 58120 Château-Chinon ville…

€111k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 22 May 2025 · ended around July 2026 · 14 months

That is at most ~€95k a year on average: a maximum too.

Company selected

Les Forges du MorvanFabrication de structures métalliques et de parties de structures · registered office Luzy (58170) · headcount 10 to 19 employees · SIREN 412264111

The competition

22 bids received

Median for this procedure in 2025: 3 bids, across 49612 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 22 by amount of the 44 contracts Château-Chinon (Ville) published for 2025.

Other contracts of Les Forges du Morvan in Château-Chinon (Ville)

Complexe scientifique et astronomique : serrurerie et métallerie2025 · maximum over 14 months365€kTransformation de deux bâtiments en ERP à Château-Chinon : serrurerie…2025 · maximum over 14 months365€kCréation complexe scientifique et astronomique lot 3charpente métallique2025 · maximum over 14 months111€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Environmental considerations : Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.