Public contracts of Châteaugiron · 2019 · Construction and buildings

Il n’est pas prévu de décomposition en lot

Durée d’exécution 5 mois dont 2 mois études et 3 mois travaux · Budget conception réalisation alloué 100 000 € HT

€11k
maximum contract amount over 18 months — what was paid on it is not published
Signed on 24 September 2019 · ended around March 2021 · 18 months

That is at most ~€8k a year on average: a maximum too.

Company selected

—Travaux de maçonnerie générale et gros œuvre de bâtiment · registered office Ernee (53500) · headcount 50 to 99 employees · SIREN 378008924

The competition

4 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 3 by amount of the 6 contracts Châteaugiron published for 2019.

Other contracts of in Châteaugiron

Construction d’une salle de gymnastique, d’une salle d’escalade, d’un…2021 · maximum over 2.5 years67€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : 3

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.