Public contracts of Chelles · 2024 · Construction and buildings

Installation d’éclairage public

€200k
framework agreement: a maximum envelope for orders over 3 years, not spending — what was paid on it is not published
Signed on 9 January 2024 · running until about January 2027 · 3 yrs
Ongoing9 Jan 2027

That is at most ~€67k a year on average: a maximum too.

Company selected

Dubost Réseaux Travaux PublicsConstruction de réseaux électriques et de télécommunications · registered office Saint-Florentin (89600) · headcount 50 to 99 employees · SIREN 385194444

A contract awarded to 3 holders; above, the main holder. With it: SPIE Citynetworks, Entr Rationnelle Installation Électrique. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

16 bids received

Median for this procedure in 2024: 3 bids, across 48741 comparable contracts. Simplified procedure · awarded to 3 companies

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 32 by amount of the 65 contracts Chelles published for 2024.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.