Skip to main content

Public contracts of Cherbourg-en-Cotentin · 2024 · Construction and buildings

Construction club house RCCH

Gros oeuvre

€250k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 22 October 2024 · ended around December 2025 · 14 months

That is at most ~€214k a year on average: a maximum too.

Company selected

Leduc SASTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Virandeville (50690) · headcount 50 to 99 employees · SIREN 312454515

The competition

2 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 53 by amount of the 138 contracts Cherbourg-en-Cotentin published for 2024.

Other contracts of Leduc SAS in Cherbourg-en-Cotentin

Démolition reconstruction des vestiaires et tribunes au stade jean…2025 · maximum over 13 months125€kTravaux d’aménagement et mise en conformité thermique accessibilité du…2023 · maximum over 2 years1.3€MTravaux d’aménagement et de mise en conformité thermique…2023 · maximum over 2.5 years547€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 5

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.