Public contracts of Chiconi · 2021 · Construction and buildings

Réhabilitation de l’école

€162k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 1 March 2021 · ended around March 2023 · 2 yrs

That is at most ~€81k a year on average: a maximum too.

Company selected

MenuiprosFabrication de portes et fenêtres en métal · registered office Bandrele (97660) · SIREN 513205716

Number 11 by amount of the 30 contracts Chiconi published for 2021. It belongs to the policy Schools.

Other contracts of Menuipros in Chiconi

Réhabilitation de l’école2020 · maximum over 2 years76€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.