Skip to main content

Public contracts of Chirongui · 2021 · Construction and buildings

Extension de l’école maternelle de 6 salles de classe : terrassement et voirie et réseaux divers

€159k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 4 October 2021 · ended around October 2023 · 2 yrs

That is at most ~€79k a year on average: a maximum too.

Company selected

Kaya SARLTravaux de terrassement courants et travaux préparatoires · registered office Sada (97640) · SIREN 798954640

Number 8 by amount of the 27 contracts Chirongui published for 2021. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.