Construction hors site du MUTLI-accueil souris verte

Number 13 by amount of the 120 contracts Cholet awarded in 2026.

Contract · Construction and Bâtiment · Travaux · carried out in 49321 · environmental clauses

1.4€M
contract ceiling — what was paid on it is not published
Signed on 9 September 2026 · running until about June 2027 · 0.8 yrs
Ongoing10 Jun 2027

Who won it

SocovalSIREN 350490686

The competition

2 bids received

Adapted procedure · awarded to 3 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendments7
Subcontracting declaredyes
Environmental considerationsClause environnementale, Critère environnemental

Other contracts of Socoval in Cholet

Construction d un bâtiment fabrique hors site pour accueil du CAE du PSB20251M€Construction d un bâtiment fabrique hors site pour accueil du CAE du PSB20231.1M€Construction d un bâtiment fabrique hors site pour accueil du CAE du PSB20222.1M€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method