Public contracts of Clamart · 2023

Travaux rénovation menuiseries école rochers

Number 9 by amount of the 31 contracts Clamart awarded in 2023.

Contract · Construction and Bâtiment · carried out in 92140

277k €
contract ceiling — what was paid on it is not published
Signed on 6 October 2023 · ended around September 2024 · 0.9 yrs
Ended5 Sept 2024

Who won it

Norba Ile de France SudSIREN 509433819

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme
Published amendmentsnone

Other contracts of Norba Ile de France Sud in Clamart

Travaux rénovation menuiseries extérieures école mairie2024406k€Travaux rénovation menuiseries extérieures école mairie2023366k€