Public contracts of Cocheren · 2024 · Construction and buildings

Rénovation et restructuration du centre social Daniel Balavoine : démolition et gros œuvre

€579k
maximum contract amount over 16 months — what was paid on it is not published
Signed on 26 October 2024 · ended around February 2026 · 16 months

That is at most ~€434k a year on average: a maximum too.

Company selected

SaribatTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Norroy-Le-Veneur (57140) · headcount 10 to 19 employees · SIREN 431948116

The competition

66 bids received

Median for this procedure in 2024: 3 bids, across 48728 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 2 by amount of the 29 contracts Cocheren published for 2024.

Other contracts of Saribat in Cocheren

Démolition et gros œuvre2024 · maximum over 16 months610€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : none

Subcontracting declared : no

Social considerations : Clause sociale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.