Groupe scolaire brant : amélioration énergétique, mise en accessibilité et création d’une chaufferie : Lot 10 : Menuiseries intérieures

Number 88 by amount of the 110 contracts Colmar awarded in 2020.

Contract · Construction and Bâtiment · carried out in 68021

28k €
contract ceiling — what was paid on it is not published
Signed on 20 August 2020 · ended around October 2020 · 0.2 yrs
Ended20 Oct 2020

Who won it

Roelly-BentzingerSIREN 916820640

The competition

Number of bids not published for that year: the field is only systematic from 2024.

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceFerme
Published amendments1

Other contracts of Roelly-Bentzinger in Colmar

Travaux de rénovation des sanitaires de l’école élémentaire Saint-Exupéry202678k€Construction du gymnase BRANT (bâtiment de niveau Passif et à énergie positive): Lot 7: Menuiseries intérieures bois / Agencement2024743Rénovation et création de volets au Musée Bartholdi202353k€Accord-cadre multi-attributaires à bons de commande pour des travaux d’entretien sur bâtiments municipaux: Lot 3: Menuiserie20221M€Mise en accessibilité de l’école élémentaire pfister 2: Lot 2 : Menuiserie intérieure bois202232k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method