Travaux pour la rénovation de l’école de sainte marine

Cloisons sèches / faux plafonds et isolation

€112k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 17 June 2026 · running until about February 2027 · 8 months
Ongoing16 Feb 2027

Company selected

Construction Rodriguez-GegoTravaux de plâtrerie · registered office La Foret-Fouesnant (29940) · headcount 20 to 49 employees · SIREN 418266896

Number 5 by amount of the 6 contracts Combrit published for 2026. It belongs to the policy Schools.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.