Public contracts of Combs-la-Ville · 2025
Le projet porte sur des travaux de réhabilitation du dojo existant et la création d’une salle multisports. - Maçonnerie - Gros œuvre - VRD
The largest contract Combs-la-Ville awarded in 2025, out of 25.
Original label (DECP) : « Le projet porte sur des travaux de réhabilitation du dojo existant et la création d’une salle multisports. - Maçonnerie - Gros œuvre - VRD » · Contract · Construction and Bâtiment · Travaux · carried out in 77
723k €
contract ceiling — what was paid on it is not published
Who won it
Sme ConstructionSIREN 339262487The competition
5 bids received
Adapted procedure · awarded to 1 company
Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.
The form of the contract
PriceForfaitaire
Published amendments3
Subcontracting declaredyes
Other contracts of Sme Construction in Combs-la-Ville
La présente consultation concerne l’extension du complexe sportif Salvador Allende. Surface approximative de 557 mètres carrés (surface de plancher) neuve. - Gros oeuvre, maçonnerie, terrassement2023410k€Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.