Skip to main content

Public contracts of Compreignac · 2023 · Construction and buildings

Construction maison médicale

Plâtrerie isolation faux plafonds

€94k
contract ceiling — what was paid on it is not published
Signed on 27 March 2023 · ended around January 2024 · 10 months

Who won it

Entreprise VillemonteilConstruction d'autres bâtiments · registered office Couzeix (87270) · headcount 100 to 199 employees · SIREN 450873211

Number 6 by amount of the 7 contracts Compreignac published for 2023.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Construction maison médicale: €94k, Compreignac 2023 · Qipu