Skip to main content

Public contracts of Condé-Northen · 2020 · Professional services

Maîtrise d’oeuvre pour la restructuration et l’extension du groupe scolaire à Condé-Northen

€137k
contract ceiling — what was paid on it is not published
Signed on 30 March 2020 · ended around May 2020 · 2 months

Who won it

Blesch Cayre ArchitectesActivités d'architecture · registered office Nancy (54000) · headcount 3 to 5 employees · SIREN 824480487
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.