Construction gym taillis - chauffage ventilation plomberie

Number 9 by amount of the 40 contracts Corbas awarded in 2026.

Original label (DECP) : « Construction gym taillis - chauffage ventilation plomberie » · Contract · Construction and Bâtiment · Travaux · carried out in 69960 · environmental clauses

268k €
contract ceiling — what was paid on it is not published
Signed on 3 September 2026 · running until about February 2027 · 0.4 yrs
Ongoing2 Feb 2027

Who won it

2B ClimSIREN 480990142

The competition

8 bids received

Adapted procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

View the consolidated DECP (data.gouv.fr) ↗

The form of the contract

PriceForfaitaire
Published amendments4
Subcontracting declaredyes
Environmental considerationsCritère environnemental

Other contracts of 2B Clim in Corbas

Construction d’un gymnase au stade des Taillis à Corbas - Relance Lot 11 - Chauffage Ventilation Plomberie2024266k€

Marchés de plus de 40 000 € HT déclarés à la notification (DECP) : montants des contrats, pas les paiements. Les plus petits marchés ne sont pas publiés ; les montants manifestement erronés sont écartés.

Source: Public procurement — DECP (data.gouv.fr)·Data·Method