Courbevoie: spending by policy area · 2025
Town planning and housing
€20M
8% of 2025 spending · €242 per resident
€22M in 2024
Breakdown of this item’s spending
Click a line to see what it is made of
The 2 other items (< 1%)
Largest works since 2023
Click a building site to see the contract
- Travaux de réaménagement du parc de Becon : secteur nord-est : espaces verts et jeux2023 · Espace Deco€498k
- Travaux pour l’aménagement du parc delage a Courbevoie2025 · Idverde (IDF Sud Ouest Création)€411k
- Travaux pour l’aménagement du square des trois frères enghels a Courbevoie et de ses abords2024 · Quesnot Paysage€192k
Who won this item’s contracts since 2023
Compared with towns of the same size
4.4% of the town’s running costs goes to this item. Towns of the same size: 6.9%.