Skip to main content

Public contracts of Courrières · 2025 · Construction and buildings

Structure couverte avec deux terrains de tennis-padel au stade Gabriel Péri : aménagements sportifs

€335k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 27 January 2025 · ended around July 2025 · 6 months

Company selected

Pinson Paysage NordServices d'aménagement paysager · registered office Fretin (59273) · headcount 100 to 199 employees · SIREN 487730376

The competition

5 bids received

Median for this procedure in 2025: 3 bids, across 49692 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

The largest of the 17 contracts Courrières published for 2025.

Other contracts of Pinson Paysage Nord in Courrières

Stade Gabriel Péri : terrain de football synthétique, terrains…2024 · maximum over 6 months1.1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Environmental considerations : Critère environnemental

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.