Public contracts of Couzon-au-Mont-d'Or · 2019 · Construction and buildings

Chauffage ventilation plomberie

Travaux pour la réhabilitation thermique et mise aux normes accessibilité de l’École élémentaire / compléments école…

€112
maximum contract amount over 7 months — what was paid on it is not published
Signed on 14 March 2019 · ended around October 2019 · 7 months

Company selected

RabyTravaux d'installation d'équipements thermiques et de climatisation · registered office Fontaines-Sur-Saone (69270) · headcount 10 to 19 employees · SIREN 519220123

The competition

1 bid received

Median for this procedure in 2019: 3 bids, across 91 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 2 by amount of the 9 contracts Couzon-au-Mont-d'Or published for 2019.

Other contracts of Raby in Couzon-au-Mont-d'Or

Chauffage2021 · maximum over 9 months179€
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.