Restauration de la façade de la Chapelle de la Visitation Sainte-Marie

€21k
maximum contract amount over 6 months — what was paid on it is not published
Signed on 1 September 2021 · ended around March 2022 · 6 months

Company selected

Beaufils Couverture - CharpenteTravaux de couverture par éléments · registered office Saint-Etienne (42000) · headcount 50 to 99 employees · SIREN 521241356

Number 9 by amount of the 10 contracts Crest published for 2021.

Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Ferme et actualisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.