Public contracts of Créteil · 2018 · Professional services

Maîtrise d'Œuvre pour la création d’un troisième Tube entre l’usine de valorisation énergétique et le réseau de chauffage urbain

€121k
maximum contract amount over 14 months — what was paid on it is not published
Signed on 8 October 2018 · ended around December 2019 · 14 months

That is at most ~€104k a year on average: a maximum too.

Company selected

ManergyIngénierie, études techniques · registered office Creteil (94000) · headcount 100 to 199 employees · SIREN 328581822

Number 12 by amount of the 26 contracts Créteil published for 2018.

Other contracts of Manergy in Créteil

Maîtrise d'Œuvre pour l’extension dite du grand colombier du réseau de…2021 · maximum over 2 months135€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.