Public contracts of Dembeni · 2026 · Construction and buildings

Divers surcoûts liés à larrêt du chantier du groupe scolaire t22 à hajangoua

Fluides

€44k
maximum contract amount over 12 months — what was paid on it is not published
Signed on 11 August 2026 · running until about August 2027 · 12 months
Ongoing11 Aug 2027

Company selected

Gca MayotteTravaux d'installation d'équipements thermiques et de climatisation · registered office Mamoudzou (97600) · SIREN 844780247

The competition

1 bid received

Median for this procedure in 2026: 3 bids, across 23525 comparable contracts. Simplified procedure · awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 11 by amount of the 13 contracts Dembeni published for 2026.

Other contracts of Gca Mayotte in Dembeni

Divers surcoûts liés à larrêt du chantier du groupe scolaire t22 à…2026 · maximum over 12 months75€kRéhabilitation, extension et réfectoire du groupe primaire…2023 · maximum over 2 years566€kRéhabilitation, extension et création d’un réfectoire du groupe…2022 · maximum over 2 years398€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.